| Name of Project : AL-Khidr Bridge
Estimated Cost : ID 232,000,000
Duration of Remaining Works : 182 Days
Date of Start : 1 / 9 / 2003
Contractual Date of Completion : 3 / 4 / 2004
Expected Date of Completion : 30 / 6 / 2004
Location : AL-Muthana Governorate, AL-Khidr City
Client : State Commission of Roads and Bridges
Description and Scope of Work : The Bridge was bombed in the Gulf war 2 and was repaired by introducing a Universal Bridge on one of its 36 m end span the scope of the new work includes the removal of the Universal Bridge, bisecting the damaged span in two spans of 18 m Length by introducing a middle pier and constructing a composite concrete bridge in replacement, also finishing the pavement and sidewalks and Fences.
Progress percentage of remaining work: 95%
Total Manpower
Company staff : 3
Contractors staff : 12
Addition work : Adding a retaining wall on the eastern part of the bridge 75 m L, Height varying from 6-7.5 m .
Note: The work was delayed in the manufacturing of steel girders because of shortage of Electricity and Oxygen for cutting machines.
|