Name of Project : AL-Muthana Bridge

Estimated Cost : ID 318,000,000 (include additional work)

Duration : 185 Days

Date of Start : 1 / 8 / 2003

Contractual Date of Completion : 12 / 1 / 2004

Expected Date of Completion : 1 / 5 / 2004

Location : Baghdad Governorate on Tigris River North of Baghdad City.

Client : State Commission of Roads and Bridges

Description and Scope of Work : A four span concrete bridge total Length 40 m (2 x 8 + 2 x 2) and 25 m Width. The work includes the ismantling of the deck slab and 12 columns and central pile cap and the repair of 8 piles and recasting the bridge in accordance of its original design including Sidewalks and Fences.

Progress percentage: 99%

Total Manpower Company staff : 8

Contractors staff : 15

Note :

1) This Bridge was damaged by blasting done by the Iraqi Army during the war .

2) The work was delayed because of the need of evaluation of the damage pile cap and redesign of it and partial because the subcontractor failed in his obligation.