Name of Project : Box Culverts

Estimated Cost : ID 1,396,800,000

Duration of Remaining Works : 183 Days

Date of Start : 1 / 10 / 2003

Date of Completion : 31 / 3 / 2004

Location : Thi-Qar Governorate Express Way (1) Section (6).

Client : State Commission of Roads and Bridges

Description and Scope of Work : Box Culverts of various dimensions varying from (1.5 x 3)m to (3 x 5)m single and double the total estimated quantities of concrete was 8500 m 3 and earth works 55000 m 3 . The remaining works are left back parts in 10 Culverts out of total number 24 Culverts of a total amount of concrete 322.5 m 3 plus a new Box Culvert on an oil pipe line.

Progress percentage of remaining work: 40 %

Total Manpower Company staff : 2

Contractors staff : 10

Note:

* The work will be delayed because the embankment is used by the Coalition Forces tropes and trailers and the work were held officially from 14/2/2004 for the above reason.

* The work has been suspended effecting from 27-1-2004 by residence engineer instruction.