Name of Project : AL-Suwair Bridge

Estimated Cost : ID 267,805,000

Duration of Remaining Works : 213 Days

Date of Start : 1 / 10 / 2003

Date of Completion : 30/ 4 / 2004

Location : Thi-Qar Governorate Express way (1) Section (6).

Client : State Commission of Roads and Bridges

Description and Scope of Work : A one span concrete bridge 20 m Length and 18.7 m Width consist of 56 precast piles (30x30 cm) 12 m deep, pile cap, Abutment and 20 prestressed girders, deck slab, Retaining walls, Side walks and Fences.

Progress percentage of remaining work: 90%

Total Manpower Company staff : 2

Contractors staff : 10

Note:

* There are additional work including construction of a detour and Excavation of the span of the bridge backfilled by the Coalition Forces.

*The delay of the work on 1- 4-2004 until the filling works for the approaches will be completed by Ashoor company.