Name of Project : College of Science and College of Information (Baghdad University) Phase 1.
Estimated Cost : ID 890,198,000
Duration : 194 Days
Date of Start : 20 / 9 / 2003
Date of Completion : 31 / 3 / 2004
Location : Baghdad Governorate, AL-Jadria
Client : State Commission of Buildings
Description and Scope of Work : The Work includes the footing, tie beams, columns, backfilling with earth and sub base, R.C. floors and part of the ground floor roof of the college of Information.
Progress percentage : 93%
Total Manpower
Company Staff : 15
Contractors Staff : 40
Note:
* The project consist of a group of two stories buildings total built up area is 64000 m 2 ,
the total cost was estimated to be 33 billion Iraqi Dinars and in 4 years duration to be
included in the Ministry of Higher Education for the following years in phases.
• There is additional period up to 15-5-2004.
•
* There is varlation order with amount of 348 million dinar.
|