Name of Project : College of Science and College of Information (Baghdad University) Phase 1.

Estimated Cost : ID 890,198,000

Duration : 194 Days

Date of Start : 20 / 9 / 2003

Date of Completion : 31 / 3 / 2004

Location : Baghdad Governorate, AL-Jadria

Client : State Commission of Buildings

Description and Scope of Work : The Work includes the footing, tie beams, columns, backfilling with earth and sub base, R.C. floors and part of the ground floor roof of the college of Information.

Progress percentage : 93%

Total Manpower Company Staff : 15

Contractors Staff : 40

Note:

* The project consist of a group of two stories buildings total built up area is 64000 m 2 , the total cost was estimated to be 33 billion Iraqi Dinars and in 4 years duration to be included in the Ministry of Higher Education for the following years in phases. There is additional period up to 15-5-2004.

* There is varlation order with amount of 348 million dinar.