| Name of Project : Road Works in Khur AL-Zubair
Free Zone
Estimated Cost : ID 1,112,900,000
Duration : 180 Days
Actual Date of Start : 15 / 1 / 2004
Date of Completion : 16 / 7 / 2004
Location : Basrah Governorate, Khur AL-Zubair
Client : State Commission of Buildings
Description and Scope of Work : Earth Works (150000) m 3 , Kerbstone for side walks (120000) m L, Asphalt pavement wearing coarse (5 cm) (144000) m 2 .
Progress percentage : 40%
Total Manpower
Company Staff : 17
Contractors Staff : 15
Note: The project was delayed in starting because of the approval entrance to site
was not issued till 4 / 1 / 2004
|