Name of Project : Road Works in Khur AL-Zubair

Free Zone Estimated Cost : ID 1,112,900,000

Duration : 180 Days

Actual Date of Start : 15 / 1 / 2004

Date of Completion : 16 / 7 / 2004

Location : Basrah Governorate, Khur AL-Zubair

Client : State Commission of Buildings

Description and Scope of Work : Earth Works (150000) m 3 , Kerbstone for side walks (120000) m L, Asphalt pavement wearing coarse (5 cm) (144000) m 2 .

Progress percentage : 40%

Total Manpower Company Staff : 17 Contractors Staff : 15

Note: The project was delayed in starting because of the approval entrance to site was not issued till 4 / 1 / 2004