The Company Achievement in 2003

The Company had the following projects in the

remaining of the year 2003 Budget

1.Ongoing projects from year 2002:
S N
Project Name
Total Cost of Project in ID 1000
2003 Budget ID 1000
Work Achiev ed ID 1000
Remarks

1

Euphrates Bridge in AL-Bat-ha Expressway (1) Section (6).
1340822
62763
135000
Tranferred to2004
2
AL-Khidr
753737
115075. 5
192000
3
AL-Mabzal Bridge Expressway (1) Section (6).
267805
36156
35000
4
AL-Suwair Bridge Expressway (1) Section (6).
1396800
376153. 5
69000
5
Box Culverts Expressway (1) Section (6).
1266057
186000
198000
6
AL-Bat-ha Intersection Expressway (1) Section (6).
383517
150000
304000
7
Bridge AL-Yousifia Intersection
696155
100500
S N
Project Name
Total Cost of Project in ID 1000
2003 Budget ID 1000
Work Achiev ed ID 1000
Remarks

8

AL-Muthana Bridge.
318000
112500
85000
Tranferred to2004
9
AL-Ramadi Connecting Bridge to expressway.
4731851
250500
163500
10
Road in Khur AL-Zubair Free Zone.
647475
436500
666000
11
College of Science and College of Information (Baghdad University).
890198
890198
12
Plastic Surgery Hospital.
178000
178000

 

271634. 6
227684 0

 

2) New projects in year 2003 Budget:
S N
Project Name
Total Cost of Project in ID 1000
2003 Budget ID 1000
Work Achiev ed ID 1000
Remarks

1

 

Rehabilitation of the Ministry of Water Resources.
5084018
262500 0
210000 0

 

2
Rehabilitation of The AL-Mutasim Company Head Quarters.
775500
775500
400000

 

340050 0
250000 0

 

3) New projects not in year 2003 Budget:
S N Project Name Total Cost of Project in ID 1000 Remarks
1 Rehabilitation of a Building for the New Iraqi Army. 192000 Completed
Summary
S N
Description
2003 Budget in ID 1000
Work Achieved

1

Ongoing projects from 2002.

2716346

2151500

2
New projects in 2003. .
3400500
2500000
3
New project not in 2003 Budget
192000
192000

 

6308846
4843500

1)Hence Percentage Achieved 76% Note:
The reason for not Achieving the Budget Amounts is due to :

1) Lack of Communication.
2) Security.
3) Delay of signing some of the contracts.
4) Delay Issuing of the Budget of some Projects.
5) Delay of Handing over the sites.
6) Changing the scope of works.
7) Change of the Designs.
8) Shortage of Electricity.
9) Fuel Shortage.
10) Traffic Jam.